All Saints Catholic School, Walthamstow
During the school summer holiday period of 2026, Bower Fuller, working as the Principal Contractor, successfully delivered a comprehensive decarbonisation and building services upgrade project at All Saints Catholic School in Dagenham, ensuring all works were completed within the limited 6-week holiday window and ready for occupation at the start of the new academic year.

The project involved the installation of new Toshiba VRF heat pump air conditioning systems serving both the Evers Block and the Science Block, providing efficient, low-carbon heating and cooling throughout the buildings. A new centralised control system was incorporated, allowing the school to monitor and manage all air conditioning units from a single location. To support the school’s sustainability objectives, a large-scale rooftop photovoltaic (45 kWp) installation was delivered, complete with all associated electrical and plant infrastructure.

As part of the wider heating system upgrade, the existing radiator and underfloor heating systems were decommissioned and replaced with radiant heating panels within the circulation corridors. Three new point-of-use water heaters were also installed within the Science Block to improve hot water provision. Significant external works included the removal of an existing pond area and the creation of new hardstanding to accommodate the VRF outdoor units, together with the construction of a secure fenced compound for the new plant.

Following completion of all mechanical, electrical and builder’s works, a full deep clean was undertaken, ensuring the facilities were handed back to the school in excellent condition and ready for immediate use

Role:

Mechanical and Electrical Contractor

Client:

All Saints Catholic School

M & E Consultant:

Bower Fuller Design & Build

Project Manager:

PCH Associates

Value:

£350K